Project Description
An expansion of existing temple by adding a 7000 sq. ft. on north side. It provides following key improvements but not limited to.
- Digital Learning Center for younger Generation
- Addition of prayer hall opposite to Ganesh Sanctum
- Installation of Dwajastambam
- All season Havan Kund
- Improved access for seniors & handicap people with addition of elevator
- Meditation Hall
- Aesthetically pleasing facility
Total Estimated Cost: $3.6 Million
Initial fundraising target is $1.6 Million. Total pledges and donations received as of 12/25/2020 were $1,357,248.00
Every dollar counts, so please donate generously!!!
Please Make Your Generous Donation Here
|
Donor Recognition:
Based on the contribution donors will be recognized in the appropriate category on the recognition board
$5,000 to $10,000;
$10,000 to $25,000;
$25,000 to $50,000;
$50,000 to $100,000
Above $100,000
Donors contributed above $100,000 towards the construction of identified areas will also be recognized with their wish in areas.
Project Execution Milestone Dates:
All the upcoming activities and dates are subject to be modified as more progress made. Activities completed are listed in bold and green color.
- Inauguration celebrations completed from 5/27/2021 to 5/31/2021 and expanded facility is being used
- Project Completion Spring 2021.
- Start of construction July 1st 2019
- Bid Review, Negotiations and Signing contract Mid-April 2019
- Bidding for Construction will require 6 weeks (Mid-March 2019)
- City and State review & approval by Jan’19 end
- Expect Completion of all Construction Documents by Mid-Dec’18
- Bhoomi Pooja Ceremony of project – Nov 18th 2018
- Temple Expansion Project fundraising dinner – Oct 28th 2018
- City Planner issued project approval letter on Oct 19, 2018
- Inland Wetland Commission at their August meeting determined no Public Hearing required and issued permit on Sept 5, 2018
- After initial review City determined that an Inland Wetland Permit is required. Application submitted on July 23, 2018
- Architect submitted Site Plan on June 2018 for the City approval
- Architect’s Agreement signed on Dec 12, 2017
- BOT/EC on Dec 3, 2017 formed a Building Committee of 7 members
Contact Us
Please contact below for additional details on the project
Construction Committee Chair: Sudhir Shah 860.918.5326
Fundraising Committee Chair: Adish Jain 860.218.5269
Chairman: Dr. Surendra Chawla 860.558.1631
President: Mr. Kiran Pyneni 860.970.7583
©2015-18 Sri Satyanarayana Swamy Temple (Connecticut Valley Hindu Temple Society)